11/30 PROGRESS REPORT & READY FOR DRYWALL

The siding is almost on the dorm.

South, north, and east sides are done. West side should be on Friday or Saturday.

Ready for drywall.

All electrical, plumbing, and heating are in walls and ceilings, and ready for drywall.